Three Major Functions
Planning
The flow of work through each of the
work centers must be planned to meet delivery dates. So, the production must
first, ensure that the required materials, tooling, personnel, and information
are available to manufacture the components when needed. Second, schedule
starts and completion dates for each shop order at each work center so the
scheduled completion dates of the order can be met. This will involve the
planner in developing a load profile.
Implementation
After the plans are made, the PAC
must make the plans into an action by give the shop floor what must be done. The
PAC usually give an instruction by issuing a shop order such as; gather the
information needed by the shop floor to make the product. Then, release orders
to the shop floor as authorized by the material requirements plan. This is
called dispatching.
Control
Once plans are made and shop orders released, the
process must be monitored to learn what is actually happening. The PAC wiil do,
rank the shop orders in desired priority sequence by work center and establish
a dispatch list based on this information. Then, monitor and control wok-in-process,
lead times, and work center queues.
Credit by : Zulaikha
Credit by : Zulaikha
Comments
Q: Anonymous said…
i wanted to ask, why do we need control in PAC?
A: We need control in PAC because we need to control if the production have any delay, damage or etc.